Design and implementation of a minigrid solution

Late availability of grid connection threatened commissioning schedule of offshore wind park potentially resulting in delays for WEC EPCI supplier with potential knock-on effects for operator (impact on LD claim)
  • cost benefit analysis including comprehensive risk
    identification and assessment
  • design and implementation of so called minigrid solution, i.e. providing power via gensets installed on separate barge being connected to the offshore substation.
  • Management of supplier and coordination of all interfaces between BoP and WEC package
  • Definition, implementation, and supervision of required electrical safety concept